Report for November 2014
- Report Date
- November 2014
Achievements in Last Period
- Developed stakeholder map and communication plan.
- Held user group workshops to establish detailed requirements for first strand of project: communication of progression
- Developed user stories for first strand
- Started development of progression processing
- Investigated use of automated testing tools
- Developed mapping from SMART to EUCLID assessment structures
- Arranged school visits for analysis of existing assessment systems and processes
Issues
- Brief not submitted to WIS as planned. The briefing paper has been previously signed off by Student Systems Board and Steering group. To be submitted to WIS for 5/12. See https://www.projects.ed.ac.uk/project/sac034/issues/3
Next Steps
- Submit brief
- Further development of strand 1
- Further analysis of strand 2 requirements : draw up list of requirements and estimates
- School visits for analysis of existing assessment systems and processes
- Wider communication to School reps
- Meet with Tribal to discuss options for Tribal contribution to build
- Approved budget
- 200.0 days
- Activity this month
- 35.5 days
- Activity this year
- 72.0 days
- Activity to date
- 72.0 days
- Estimate to complete current year
- 128.0 days
- Estimate to complete future years
- 0.0 days