Report for November 2014

Report Date
November 2014

Achievements in Last Period

  • Developed stakeholder map and communication plan.
  • Held user group workshops to establish detailed requirements for first strand of project: communication of progression
  • Developed user stories for first strand
  • Started development of progression processing
  • Investigated use of automated testing tools
  • Developed mapping from SMART to EUCLID assessment structures 
  • Arranged school visits for analysis of existing assessment systems and processes

 

Issues

Next Steps

  • Submit brief 
  • Further development of strand 1 
  • Further analysis of strand 2 requirements : draw up list of requirements and estimates
  • School visits for analysis of existing assessment systems and processes
  • Wider communication to School reps
  • Meet with Tribal to discuss options for Tribal contribution to build

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
35.5 days
Activity this year
72.0 days
Activity to date
72.0 days
Estimate to complete current year
128.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary