Report for December 2016

Report Date
December 2016

Achievements in Last Period

None

Resolved issues

None

 

Open Issues

Issue 46 Change in closure milestone date

 

Next Steps

  • Close project
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
RED due to missed closure milestone.
Change Status
Activity
Approved budget
834.0 days
Activity this month
0.0 days
Activity this year
6.0 days
Activity to date
865.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary