Report for July 2016
- Report Date
- July 2016
Achievements in Last Period
- Completed development of reassessment for August resits
- Started briefing pilot schools on reassessment
- Supported final S2 exam board
- Documentation for handover to support
- Held sessions with student group for development of student view of assessments
- Held first of two pilot review sessions
Resolved issues
- None
Open Issues
- None
Next Steps
- Documentation for handover to support
- Closure
- And for the new APT project Foundations for APT project for 2016/17
- Foundations
- Support of resit boards for pilot schools
- development of Barcodes, Student view of component marks and set up of pass/fail courses
Milestones
- Approved budget
- 834.0 days
- Activity this month
- 26.0 days
- Activity this year
- 403.0 days
- Activity to date
- 860.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 4.0 days