Report for June 2016

Report Date
June 2016

Achievements in Last Period

  • Supported pilot schools through exam boards
  • Develop reassessment functionality for August resit diet
  • Delivered enhancments/fixes to assessment and progression & awards tools 
  • Input to Service Excellence programme & participatee in relevant workshops 
  • Positive feedback received from pilot schools about the tools developed to date, the collaborative way of working and the support provided by the project team.

 

Resolved issues

 

 

Open Issues

  • None

Next Steps

  • Complete development of reassessment for August resits
  • Brief pilot schools on reassessment
  • Documentation for handover to support
  • Hold sessions with student group for development of student view of assessments
  • Hold review sessions for S2 exam boards
  • Project planning for 16/17
  • Prepare for project closure

Milestones

Target dateTitle
05-Aug-2016Review S2 exam boards
30-Aug-2016Close
27-Sep-2016Deployment of sub component ratification and publication, and student and staff views (to be delivered in next year's project)

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
20.0 days
Activity this year
377.0 days
Activity to date
834.0 days
Estimate to complete current year
41.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary