Report for June 2016
- Report Date
- June 2016
Achievements in Last Period
- Supported pilot schools through exam boards
- Develop reassessment functionality for August resit diet
- Delivered enhancments/fixes to assessment and progression & awards tools
- Input to Service Excellence programme & participatee in relevant workshops
- Positive feedback received from pilot schools about the tools developed to date, the collaborative way of working and the support provided by the project team.
Resolved issues
- Change of milestone date for S2 exam board reviews
- Change of Project closure date
- Move of milestone 'Deployment of sub...
Open Issues
- None
Next Steps
- Complete development of reassessment for August resits
- Brief pilot schools on reassessment
- Documentation for handover to support
- Hold sessions with student group for development of student view of assessments
- Hold review sessions for S2 exam boards
- Project planning for 16/17
- Prepare for project closure
Milestones
Target date | Title |
---|---|
05-Aug-2016 | Review S2 exam boards |
30-Aug-2016 | Close |
27-Sep-2016 | Deployment of sub component ratification and publication, and student and staff views (to be delivered in next year's project) |
- Approved budget
- 0.0 days
- Activity this month
- 20.0 days
- Activity this year
- 377.0 days
- Activity to date
- 834.0 days
- Estimate to complete current year
- 41.0 days
- Estimate to complete future years
- 0.0 days