October 2014
- Report Date
- October 2014
Achievements in Last Period
- Project briefing produced and presented to Student Systems Board and CSPC Assessment and Progression working group
- Tribal consultancy on awards and progression processes
- Held Project Inception Meeting with key stakeholders
- Prototyping of potential screens
- Mapping of SMART assessment structures
- Creation of user groups
- Set up project wiki
Issues
None
Next Steps
- Develop communication plan following discussions at inception meeting.
- Sign off project brief.
- User group meetings - establish high level requirements list and detailed requirements for first strand of project: communication of progression
- School visits for analysis of existing assessment systems and processes
- Start development of progression processing
- Produce estimates and release plan
- Approved budget
- 200.0 days
- Activity this month
- 22.5 days
- Activity this year
- 36.5 days
- Activity to date
- 36.5 days
- Estimate to complete current year
- 163.4 days
- Estimate to complete future years
- 0.0 days