Report for February 2016
- Report Date
- February 2016
Achievements in Last Period
- Started Award and Progresssion development
- Developed enhancements to course set up and SMART migration so that process can be run by Student Systems (saving Dev Tech resource)
- Developed initial functions for dropping items of assessment
- Carried out review of exam boards with Schools
- Technical review of board reports : BI Suite v EUCLID
- Investigated use of StuTalk/services for exposing data for MyEd channels (and potentially LEARN, EUCLID staff and student views)
- Comms: presented 4 wider college briefings
- Transition planning: meetings set up with group 2 schools moving onto APT for 2016/17 to agee plan for rest of 2016
- Delivered course set up training of schools to 4 group 2 schools
Resolved issues
- Impact of sickness absence of SSP IS team leader
- Impact of Live performance issues
- Change of Sponsor
- Change of milestone for S1 exam board review
- Behind plan on Progression and Award processing resolved at 2/3
Open Issues
Next Steps
- Set up courses and migrate SMART courses for schools moving onto APT for 2016/17
- Develop functionality to support straight through progression and award process
- Work with software supplier to set up progression and award rules for pilot programmes
- Define strategy for reassessment development
Milestones
- Approved budget
- 834.0 days
- Activity this month
- 25.0 days
- Activity this year
- 247.0 days
- Activity to date
- 704.0 days
- Estimate to complete current year
- 143.0 days
- Estimate to complete future years
- 0.0 days