Report for January 2016
- Report Date
- January 2016
Achievements in Last Period
- Finished development and deployed marks rattification, publishing and amendment for overall course marks
- Developed and deployed various enhancements to aid exam board preparation
- Complete changes, test and deploy BI universe, board report and basic programme report
- Initial analysis for MyEd channel replacement
- Provided training for pilot schools for January exam boards
- Provided ongoing support for pilot schools through exam boards
- Met with key academic and administrative contacts in group 1 and 2 schools
- Drew up transition plan for group 1 & 2 schools for 2016-17
Resolved issues
- https://www.projects.ed.ac.uk/project/sac034/issues/30 Increase to project budget
Open Issues
- https://www.projects.ed.ac.uk/project/sac034/issues/21 Difficulty engaging with software supplier. Met with software supplier, awaiting response to requests.
- https://www.projects.ed.ac.uk/project/sac034/issues/32 Impact of LIVE performance issues on the project
- https://www.projects.ed.ac.uk/project/sac034/issues/31 Impact of sickness absence of SSP IS team leader
Next Steps
- Analysis of Award and Progresssion flows and start development
- Enhance course and SMART migration
- Set up courses and migrate SMART courses for schools moving onto APT for 2016/17
- Develop dropping items of assessment
- Review exam boards with Schools and plan required enhancements
- Carry out technical review of board reports : BI Suite v EUCLID
- Investigate use of StuTalk/services for exposing data for MyEd channels (and potentially LEARN, EUCLID staff and student views)
- Wider college briefings
- Start course set up training of schools moving onto APT for 2016/17
Milestones
12-Feb-2016 | Review of S1 exam boards |
31-May-2016 | Deployment of MyEd channel replacement |
01-Jul-2016 | Review S2 exam boards |
01-Aug-2016 | Deployment of sub component ratification and publication, and student and staff views |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days