Report for November 2015

Report Date
November 2015

Achievements in Last Period

  • Provided ongoing support for pilot schools 
  • Met with software supplier to discuss potential enhancements to core product
  • Completed initial analysis and scoping for work for DPT maintenance

 

  • Developed and released the following to LIVE
    • Test assessment structure
    • Navigation and usability improvements
    • Performance enhancements to marks export
    • Flagging of reassesemnt methods
    • Locking of assessment set up when marks have been entered

 

Resolved issues

  • none

Open Issues

 

Next Steps

  • Complete changes, test and deploy BI universe and board report 
  • Finish development, test and deploy marks rattification, publishing and amendment for overall course marks
  • Prepare training for users for January exam boards
  • Review project milestones for rest of 2015/16
  • Meet with key academic and administrative contacts in group 1 and 2 schools

 

Target dateTitle
18-Dec-2015Deployment of course boards requirements
12-Feb-2016Review of S1 exam boards
05-Apr-2016Deployment of Progression/Classification board requirements
28-Jul-2017Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
810.0 days
Activity this month
60.0 days
Activity this year
184.0 days
Activity to date
641.0 days
Estimate to complete current year
175.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary