Report for November 2015
- Report Date
- November 2015
Achievements in Last Period
- Provided ongoing support for pilot schools
- Met with software supplier to discuss potential enhancements to core product
- Completed initial analysis and scoping for work for DPT maintenance
- Developed and released the following to LIVE
- Test assessment structure
- Navigation and usability improvements
- Performance enhancements to marks export
- Flagging of reassesemnt methods
- Locking of assessment set up when marks have been entered
Resolved issues
- none
Open Issues
- https://www.projects.ed.ac.uk/project/sac034/issues/21 Difficulty engaging with software supplier. Met with software supplier, awaiting response to requests.
Next Steps
- Complete changes, test and deploy BI universe and board report
- Finish development, test and deploy marks rattification, publishing and amendment for overall course marks
- Prepare training for users for January exam boards
- Review project milestones for rest of 2015/16
- Meet with key academic and administrative contacts in group 1 and 2 schools
Target date | Title |
---|---|
18-Dec-2015 | Deployment of course boards requirements |
12-Feb-2016 | Review of S1 exam boards |
05-Apr-2016 | Deployment of Progression/Classification board requirements |
28-Jul-2017 | Close |
- Approved budget
- 810.0 days
- Activity this month
- 60.0 days
- Activity this year
- 184.0 days
- Activity to date
- 641.0 days
- Estimate to complete current year
- 175.0 days
- Estimate to complete future years
- 0.0 days