Report for September 2015

Report Date
September 2015

Achievements in Last Period

  • Built 'recording reasons for changes to marks'  
  • Built changes to course roll forward for assessment structures
  • BI Universe enhancments made to support board reports
  • Re-assessment analysis and consultancy
  • Prepared draft proposed board processes for consideration at workshop at beginning October
  • Inducted new Student Systems Operations staff member who will be responsible for business support for the new system
  • Provided support for pilot schools

Issues

  • The project is being disrupted by the impact of developer leaving. See issue 27
  • Progress wasn't as good as expected during this period due to lead developer having to deal with unforseen issues arising whilst Defeng Ma was on annual leave. See issue 28 
  • It is likely that additional work will have to be carried out to accommodate calculation of Grade Point Averages. This is seen as a risk to the project see risk 11

 

Next Steps

  • Test and deploy record changes to marks and course roll forward
  • Develop marks status flags functionality
  • Develop changes to existing marks upload
  • Develop board reports
  • Design and start build on re-assssment functionality
  • Analysis of 'elevated hurdles' and other DPT anomalies ane present to steering group.
  • Produce papers for CPSC for proposed key dates, exam board processes and data required at each exam board so that these can can be adopted across the institution.
  • Meet with group 2 schools individually and support pilot schools entering S1 asessment marks

 

Milestones

Target dateTitle
18-Dec-2015Deployment of course boards requirements
12-Feb-2016Review of S1 exam boards
05-Apr-2016Deployment of Progression/Classification board requirements
29-Jul-2016Close
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
790.0 days
Activity this month
27.2 days
Activity this year
74.9 days
Activity to date
532.0 days
Estimate to complete current year
258.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary