Report for August 2015
- Report Date
- August 2015
DRAFT
Achievements in Last Period
- Gained acceptance sign off for pilot from all Schools and go ahead from Steering Group
- Delivered fixes/enhancements
- Reviewed project with project team and student systems director (lessons learned) and gained feedback from schools on strand 1.
Issues
- Coldfusion 9 is due to be decommissioned in July 2016. With the current project rollout schedule, all schools are expected to migrate from SMART from September 2016. Some analysis required round access to historical SMART data. See https://www.projects.ed.ac.uk/project/sac034/issues/12 Checkpoint milestone created for February 2016 : SMART decommissioning checkpoint
Next Steps
- Develop 'recording reasons for changes to marks', double marking flag and status flags
- Develop board reports
- Re-assessment analysis
- Support pilot schools
- Start engagement with group 2 schools
Target date | Title |
---|---|
18-Dec-2015 | Deployment of course boards requirements |
12-Feb-2016 | Review of S1 exam boards |
12-Feb-2016 | SMART decommissioning checkpoint |
05-Apr-2016 | Deployment of Progression/Classification board requirements |
29-Jul-2016 | Close |
- Approved budget
- 790.0 days
- Activity this month
- 51.0 days
- Activity this year
- 51.0 days
- Activity to date
- 504.0 days
- Estimate to complete current year
- 279.0 days
- Estimate to complete future years
- 0.0 days