Report for July 2015

Report Date
July 2015

Achievements in Last Period

  • Support for UAT : held briefings, school visits, development of enhancements
  • Released enhancements based on user feedback 

Issues

  • None

 

Next Steps

  • Acceptance sign off and deploy pilot code to LIVE
  • Review project to date and plan for 15/16
  • Develop board reports
  • Develop double marking functionality
  • Progress set up of progression and award rules

 

Target datesort iconTitle
04-Aug-2015User Testing Review
04-Aug-2015End-to-end testing complete for strand 2 pilot
07-Aug-2015Pilot go/no go
12-Aug-2015Deploy first cut pilot code to LIVE
14-Aug-2015Checkpoint for 2015/16 work
29-Jul-2016Close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
790.0 days
Activity this month
60.0 days
Activity this year
457.0 days
Activity to date
457.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
350.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary