Report for July 2015
- Report Date
- July 2015
Achievements in Last Period
- Support for UAT : held briefings, school visits, development of enhancements
- Released enhancements based on user feedback
Issues
- None
Next Steps
- Acceptance sign off and deploy pilot code to LIVE
- Review project to date and plan for 15/16
- Develop board reports
- Develop double marking functionality
- Progress set up of progression and award rules
Target date![]() | Title |
---|---|
04-Aug-2015 | User Testing Review |
04-Aug-2015 | End-to-end testing complete for strand 2 pilot |
07-Aug-2015 | Pilot go/no go |
12-Aug-2015 | Deploy first cut pilot code to LIVE |
14-Aug-2015 | Checkpoint for 2015/16 work |
29-Jul-2016 | Close |
- Approved budget
- 790.0 days
- Activity this month
- 60.0 days
- Activity this year
- 457.0 days
- Activity to date
- 457.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 350.0 days