Report for September 2014
- Report Date
- September 2014
Achievements in Last Period
- Tribal consultancy for team
- Initial meeting of project team
- Familiarisation with Tribal software
- Preparation of briefing paper for Student Systems Board
Issues
None
Next Steps
- Further Tribal consultancy
- Complete and sign off brief. Following the withdrawal of SAC035, there is an extra 50d budget for this project (currently held in the programme balance row), to be added at the end of planning.
- First meeting of CSPC Assessment and Progression working group
- Formation of user group
30-Oct-2014 | Brief sign off |
- Approved budget
- 200.0 days
- Activity this month
- 3.6 days
- Activity this year
- 4.1 days
- Activity to date
- 4.1 days
- Estimate to complete current year
- 195.9 days
- Estimate to complete future years
- 0.0 days