September 2014
- Report Date
- September 2014
Achievements in Last Period
- KIS, HESA Student and SFC Final Figures deadlines completed
DLHE and NSS downloadable file structures - coding changes completed
The 2013/4 HESA Return has now been set to Credible and sign off from the Principal is now a formality.
Issues
- n/a
Next Steps
- Close to be brought forward in October, follow up project for 14/15 is opened
| 14-Nov-2014 | Close |
- Approved budget
- 102.0 days
- Activity this month
- 6.6 days
- Activity this year
- 10.2 days
- Activity to date
- 88.8 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days