August 2014
- Report Date
- August 2014
Achievements in Last Period
- n/a
Issues
- n/a
Next Steps
- HESA Student and Aggregate Offshore Return submission to the HESA Collection System.
Responding to HESA Data Quality issues with a view to completion by mid September
DLHE and NSS downloadable file structures - coding changes due in Sept once the files have been provided by HESA for testing in Sept (was expected end August)
| 16-Sep-2014 | KIS, HESA Student and SFC Final Figures deadlines |
| 31-Oct-2014 | Archiving and downstream loads for NSS and DLHE |
| 14-Nov-2014 | Close |
- Approved budget
- 102.0 days
- Activity this month
- 3.4 days
- Activity this year
- 3.4 days
- Activity to date
- 82.0 days
- Estimate to complete current year
- 19.0 days
- Estimate to complete future years
- 0.0 days