August 2014

Report Date
August 2014

Achievements in Last Period

  • n/a

Issues

  • n/a

Next Steps

  • HESA Student and Aggregate Offshore Return submission to the HESA Collection System.
  • Responding to HESA Data Quality issues with a view to completion by mid September

  • DLHE and NSS downloadable file structures - coding changes due in Sept once the files have been provided by HESA for testing in Sept (was expected end August)

     

16-Sep-2014KIS, HESA Student and SFC Final Figures deadlines
31-Oct-2014Archiving and downstream loads for NSS and DLHE
14-Nov-2014Close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
102.0 days
Activity this month
3.4 days
Activity this year
3.4 days
Activity to date
82.0 days
Estimate to complete current year
19.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Statutory Returns 13/14
Code
SAC020
Programme
Student Systems Partnership SSP
Project Manager
Franck Bergeret
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
19-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Oct-2014
Programme Priority
1
Category
Compliance