January 2014 Report

Report Date
January 2014
Report Date: 
 December 2013
Achievements in Last Period

1. Release 2: Transactional data removal delviery into test and acceptance testing completed. 

2. Attended Tribal Archiving and Information Governace Workshop in Newcastle. Fed back recommendations and will join reformed Archiving Group

3. Presented Archiving Documentation and Strategy used at Brunel to stakeholders Karen Osterburg and Defeng Ma. 

4. Improved awareness and knowledge of Archiving/Deletions options within SITS product

5. Scheduled initial  meeting with Iain Fiddes and Niel Grant to look at Archiving infrastructure requirements

Issues

N/A

Next Steps 1. Release 2: Setting of agreed go-Live date and scheduling resource. Deliver to Live

2. Complete writing up requirements to remove Incomplete Direct Admissions (Release 3) and non-ATR's UCAS/GTTR data (Release 4)

3. Review and amend 'Master' retention document and distribute location. 

4. Data Archiving infrastructure requirement meeting.

5. Determine options to deliver Release 3 and Release 4

Milestones

14-Feb-2014Release 4: Deletion of UCAS/GTTR Pre-ATR data - Requirements Analysis
14-Feb-2014Release 3 - Deletion on Incomplete Direct Admission Data: - Requirements analysis
18-Feb-2014Release 2: Transactional Data Deletion - Deliver to Live
11-Apr-2014Data Retention Strategy for Student Systems - Architectural overview document
11-Apr-2014Retention Schedule Review
14-Apr-2014Decision Point to determine next steps

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
70.0 days
Activity this month
3.9 days
Activity this year
23.3 days
Activity to date
23.3 days
Estimate to complete current year
46.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Retention Requirements
Code
SAC017
Programme
Student Systems Partnership SSP
Project Manager
Karen Osterburg
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jan-2016
Programme Priority
2
Category
Compliance