October 2013

Report Date
October 2013

Achievements in Last Period 1. Options Analysis O2 (Admissions Data) in progress

2. Redundant transactional tables to be added into Phase 1 of the project

3. Analysis done by Chris Giles (SSP) to identify redundant MHD/MTK records to be removed 

4. Development of scripts to remove redundant MHD/MTK records by SSP

 

Issues

N/A

Next Steps 1.Develop Options Analysis Document in full and distribute for review.

2. Testing of scripts to remove redundant MHD/MTK records in Dev

3. Scheduling Resource to test removal of redundant MHD/MTK records in TEST and to implement in Live.

4. Creation of relevant milestones.

Milestones

02-Dec-2013Options Analysis - O1 - Application and O2 - Admissions dataAnalyseNoeditview  

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
2.0 days
Activity this year
2.3 days
Activity to date
2.3 days
Estimate to complete current year
117.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Retention Requirements
Code
SAC017
Programme
Student Systems Partnership SSP
Project Manager
Karen Osterburg
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jan-2016
Programme Priority
2
Category
Compliance