October 2013
- Report Date
- October 2013
Achievements in Last Period 1. Options Analysis O2 (Admissions Data) in progress
2. Redundant transactional tables to be added into Phase 1 of the project
3. Analysis done by Chris Giles (SSP) to identify redundant MHD/MTK records to be removed
4. Development of scripts to remove redundant MHD/MTK records by SSP
Issues
N/A
Next Steps 1.Develop Options Analysis Document in full and distribute for review.
2. Testing of scripts to remove redundant MHD/MTK records in Dev
3. Scheduling Resource to test removal of redundant MHD/MTK records in TEST and to implement in Live.
4. Creation of relevant milestones.
Milestones
| 02-Dec-2013 | Options Analysis - O1 - Application and O2 - Admissions data | Analyse | No | edit | view |
- Approved budget
- 120.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.3 days
- Activity to date
- 2.3 days
- Estimate to complete current year
- 117.7 days
- Estimate to complete future years
- 0.0 days