May 2015

Report Date
May 2015

Achievements

  • Produced paper for the June Student Systems Board for agreement on a way forward.
  • Ran deletion scripts in live.

Issues

  • n/a

Next Steps

  • Arrange for scripts to be brought into Business as Usual.

 

Target dateTitle
22-Jun-2015Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Retention Requirements
Code
SAC017
Programme
Student Systems Partnership SSP
Project Manager
Karen Osterburg
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jan-2016
Programme Priority
2
Category
Compliance