September 2013

Report Date
September 2013

Achievements in Last Period 1. Brief Signed Off 2. Options Analysis O1 (Application Data) complete ready for review 3. Options Analysis O2 (Admissions Data) in progress

 

Issues

Next Steps 1.Develop Options Analysis Document in full and distribute for review.

Milestones

02-Dec-2013Options Analysis - O1 - Application and O2 - Admissions dataAnalyseNoeditview

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
0.3 days
Activity this year
0.3 days
Activity to date
0.3 days
Estimate to complete current year
119.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Retention Requirements
Code
SAC017
Programme
Student Systems Partnership SSP
Project Manager
Karen Osterburg
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jan-2016
Programme Priority
2