January 2015
- Report Date
- January 2015
Achievements
1. None
Issues
1. None
Next Steps
1. Get transactional data deletion process set up to run regularly
2. Establish retention schedule for UCAS/GTTR record deletion
| 02-Mar-2015 | Establish on-going process to delete transactional data |
| 13-Mar-2015 | Run deletion of UCAS/GTTR data in LIVE |
| 13-Mar-2015 | Establish a retention schedule for UCAS/GTTR records |
- Approved budget
- 49.0 days
- Activity this month
- 0.1 days
- Activity this year
- 1.4 days
- Activity to date
- 34.1 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days