November 2014

Report Date
November 2014

Achievements

1. None

Issues

1. None

Next Steps

1. Get transactional data deletion process set up to run regularly

2. Establish retention schedule for UCAS/GTTR record deletion

 

15-Dec-2014Establish on-going process to delete transactional data
15-Dec-2014Run deletion of UCAS/GTTR data in LIVE
15-Dec-2014Establish a retention schedule for UCAS/GTTR records

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
0.0 days
Activity this year
1.0 day
Activity to date
33.8 days
Estimate to complete current year
35.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Retention Requirements
Code
SAC017
Programme
Student Systems Partnership SSP
Project Manager
Karen Osterburg
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jan-2016
Programme Priority
2
Category
Compliance