May 2014

Report Date
May 2014

Achievements

 1.Completed running of deletion of Incomplete Direct Admissions (Release 3) in test

Issues

1. Could not run Release 3 on 20 May due to competing projects due to be run into live at the same time (Revised date w/b 23/6 https://www.projects.ed.ac.uk/project/sac017/issues/4)

Next Steps 1. Run Release 3 -Removal of incomplete Direct Admissions application data in Live

2. Handover to new BA\PM

3. Complete analysis of removal of UCAS\GTTR Pre-ATR data (Release 4) requirements analysis

 

Milestones

 

17-Jun-2014Release 4: Deletion of UCAS/GTTR Pre-ATR data - Requirements Analysis
17-Jun-2014Project Handover
24-Jun-2014Release 3 - Deletion on Incomplete Direct Admission Data: - Live

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
70.0 days
Activity this month
1.5 days
Activity this year
31.3 days
Activity to date
31.3 days
Estimate to complete current year
19.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Retention Requirements
Code
SAC017
Programme
Student Systems Partnership SSP
Project Manager
Karen Osterburg
Project Sponsor
Karen Osterburg
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jan-2016
Programme Priority
2
Category
Compliance