May 2014
- Report Date
- May 2014
Achievements
1.Completed running of deletion of Incomplete Direct Admissions (Release 3) in test
Issues
1. Could not run Release 3 on 20 May due to competing projects due to be run into live at the same time (Revised date w/b 23/6 https://www.projects.ed.ac.uk/project/sac017/issues/4)
Next Steps 1. Run Release 3 -Removal of incomplete Direct Admissions application data in Live
2. Handover to new BA\PM
3. Complete analysis of removal of UCAS\GTTR Pre-ATR data (Release 4) requirements analysis
Milestones
| 17-Jun-2014 | Release 4: Deletion of UCAS/GTTR Pre-ATR data - Requirements Analysis |
| 17-Jun-2014 | Project Handover |
| 24-Jun-2014 | Release 3 - Deletion on Incomplete Direct Admission Data: - Live |
- Approved budget
- 70.0 days
- Activity this month
- 1.5 days
- Activity this year
- 31.3 days
- Activity to date
- 31.3 days
- Estimate to complete current year
- 19.3 days
- Estimate to complete future years
- 0.0 days