Report for August 2013
- Report Date
- August 2013
Achievements in Last Period
- Brief in Draft
- User Stories created for initial phase
Issues
Next Steps
- Confirm Brief with Stakeholder
- Further Develop User Stories in the Application phase of the project
Milestones
Not yet defined, awaiting confirmation of project brief
- Approved budget
- 120.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 120.0 days
- Estimate to complete future years
- 0.0 days