Report for January 2020

Report Date
January 2020

Achievements in Last Period

  • Month End Suspended Reporting 

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • N/A

Any current or imminent risks that need to be managed:

  • Project Delivery - Due to lack of Resources/BAU
  •  

Next Steps

  • April -Project Re-opens ready to conduct 3rd and 4th Upgrade
  • IS Alert and Go-CAB Paperwork 28 Apr 20
  • Go-CAB 5 May 20
  • Upgrade prep on site due 1-22 May 20
  • Upgrade on 26-28 May 20
  • Close Project 

Future Milestones

Full Milestone Table as fist time reporting full plan

Mile

Stone

Task Name

% Complete

       Start

       Finish

6

  Project Brief produced and Signed Off

100

  07/10/19

  29/11/19

11

  Eleanor Upgrade on PROD and Test

100

  02/12/19

  06/12/19

12

  Project Suspended

100

  09/12/19

  10/04/20

13

  StackHPC Engagement for second set of Upgrades

0

  13/04/20

  17/04/20

14

  IS Alert and Go-CAB for Eleanor 2nd Upgrade Completed 

0

  28/04/20

  05/05/20

15

  RSS Systems Team prep Eleanor DEV 

0

  01/05/20

  08/05/20

16

  StackHPC Development on Eleanor DEV for 2nd Upgrade

0

  11/05/20

  15/05/20

17

  StackHPC Test Eleanor DEV for 2nd Upgrade

0

  18/05/20

  22/05/20

18

  Eleanor 2nd Upgrade on PROD and Test

0

  25/05/20

  29/05/20

19

  Delivery Complete

0

  29/05/20

  29/05/20

20

  Acceptance

0

  01/06/20

  05/06/20

21

  Closure Project

0

  08/06/20

  12/06/20

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
35.0 days
Activity this month
0.5 days
Activity this year
10.9 days
Activity to date
10.9 days
Estimate to complete current year
25.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Cloud Service
Code
RSS208
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Integrate
Status
Suspended
Project Classification
Transform
Start Date
02-Sep-2019
Planning Date
31-Oct-2019
Delivery Date
29-May-2020
Close Date
12-Jun-2020
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation