Report for December 2019
- Report Date
- December 2019
Summary
All UAT issues resolved apart new bug found in search.
Tayburn will also add the new Accessibility statement prepared for the project by Viki Galt.
Tayburn confirmed approach to deployment.
Achievements in Last Period
- Sign off UAT - done
- Deploy December - done
- Close December - will close first week January
Scope Changes
- n/a
Next Steps
- Close December
Future Milestones
| Close | Closure | 13-Jan-2020 |
Sponsor Comment
no comment for this report
- Approved budget
- 0.0 days
- Activity this month
- 21.0 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days