Report for October 2019

Report Date
October 2019

Summary

All UAT issues resolved apart from the critical requirement to have the main image on the home page interactive as a one-click process rather than the two-step of the current design in Test. New Timeline to develop this to be confirmed by Tayburn by 31/10

Tayburn will also add the new Accessibility statement prepared for the project by Viki Galt.

Tayburn will also review and confirm approach to deployment.

 

Achievements in Last Period

  • UAT completion - not completed

 

Scope Changes

  • n/a  

Next Steps

  • Fix of UAT final requirement during Oct/Nov
  • UAT completion by end of November
  • Deploy end of November  

Future Milestones

 

Deliver Work Package 1 29-Nov-2019
Deliver Work Package 2 29-Nov-2019
Close Closure 15-Dec-2019

Sponsor Comment

no comment for this report

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
one (major) requirement outstanding
Activity
Approved budget
0.0 days
Activity this month
21.0 days
Activity this year
7.0 days
Activity to date
7.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
DRS Website Development
Code
RSS050
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
06-May-2019
Planning Date
07-Jun-2019
Delivery Date
10-Dec-2019
Close Date
07-Jan-2020
Overall Priority
Highest
Category
Discretionary