Report for October 2019
- Report Date
- October 2019
Summary
All UAT issues resolved apart from the critical requirement to have the main image on the home page interactive as a one-click process rather than the two-step of the current design in Test. New Timeline to develop this to be confirmed by Tayburn by 31/10
Tayburn will also add the new Accessibility statement prepared for the project by Viki Galt.
Tayburn will also review and confirm approach to deployment.
Achievements in Last Period
- UAT completion - not completed
Scope Changes
- n/a
Next Steps
- Fix of UAT final requirement during Oct/Nov
- UAT completion by end of November
- Deploy end of November
Future Milestones
| Deliver | Work Package 1 | 29-Nov-2019 |
| Deliver | Work Package 2 | 29-Nov-2019 |
| Close | Closure | 15-Dec-2019 |
Sponsor Comment
no comment for this report
- Approved budget
- 0.0 days
- Activity this month
- 21.0 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days