Report for April 2018

Report Date
April 2018

Achievements in Last Period

  • Project completion report approval by WIS for closure
  • Project closedown complete

Issues

  • N/A

Next Steps

  • N/A

 

The project status is BLUE

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
26.0 days
Activity this month
0.0 days
Activity this year
2.3 days
Activity to date
17.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Research Information Management - Small Enhancements
Code
RES063
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
22-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Apr-2018
Programme Priority
6
Overall Priority
Normal
Category
Discretionary