Report for February 2018
- Report Date
- February 2018
Achievements in Last Period
- Project completion report in progress
Issues
- WP3 outstanding JIRA RES058-169 identified investigating whether this is still required, if so, gain agreement to cover under other RIS project to allow this project to close
Next Steps
- Close project
The project status is AMBER
| Target Date | Title |
|---|---|
| 30-March 2018 | Project Closure |
- Approved budget
- 26.0 days
- Activity this month
- 0.1 days
- Activity this year
- 1.7 days
- Activity to date
- 16.8 days
- Estimate to complete current year
- 2.9 days
- Estimate to complete future years
- 0.0 days