Report for December 2017

Report Date
December 2017

Achievements in Last Period

  • WP4 - Investigation into possible report to be created via ORACLE HR, review with RIS teamĀ purpose for access to data

Issues

  • HR views waiting for response from business areas that report view being suggested will work for them
  • Milestones will have to be extended for closure into February

Next Steps

  • WP4 - Finalise business process and correct access for resource
  • Close project

The project status is AMBER

Target Date Title
26-Jan-2018 TBC WP4 Replace RSO legacy 'HR Portal' Delivery
9-Feb-2018 Project Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
CHANGE : AMBER due to further investigation required for WP4 and milestone changes
Change Status
Activity
Approved budget
26.0 days
Activity this month
0.1 days
Activity this year
1.5 days
Activity to date
16.7 days
Estimate to complete current year
3.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Research Information Management - Small Enhancements
Code
RES063
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
22-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Apr-2018
Programme Priority
6
Overall Priority
Normal
Category
Discretionary