Report for December 2017
- Report Date
- December 2017
Achievements in Last Period
- WP4 - Investigation into possible report to be created via ORACLE HR, review with RIS teamĀ purpose for access to data
Issues
- HR views waiting for response from business areas that report view being suggested will work for them
- Milestones will have to be extended for closure into February
Next Steps
- WP4 - Finalise business process and correct access for resource
- Close project
The project status is AMBER
| Target Date | Title |
|---|---|
| 26-Jan-2018 TBC | WP4 Replace RSO legacy 'HR Portal' Delivery |
| 9-Feb-2018 | Project Closure |
- Approved budget
- 26.0 days
- Activity this month
- 0.1 days
- Activity this year
- 1.5 days
- Activity to date
- 16.7 days
- Estimate to complete current year
- 3.2 days
- Estimate to complete future years
- 0.0 days