Report for July 2017
- Report Date
- July 2017
Achievements in Last Period
- Project Brief approval completed
- WP1 required approval for use of UUN@ed.ac.uk for Staff this is needed from HR which has been provided, for students we require confirmation from Student Systems - data form has been provided and awaiting further details from approval area.
- WP8 RIS have provided guidance information and activity requires Dev Tech resource with possible Apache2 skills
Issues
- Delay in project brief sign off due to PM and intern on annual leave - this has now been approved
- WP8 Meeting held with DevelopmentTechnology and RIS resource to understand fuller requirements of this activity, however concerns raise that there may be more depth work required. Agreed to arrange a meeting with St Andrews University colleagues who are looking at this at present, this will help gauge if this actually need a larger project and more funding to complete.
- WP4 still to be investigated, likelihood this will be a business process and no technical resource required
- Review impact of delay and unplanned budget required for next financial year 17/18 review with Programme Owner and Business Lead, revise project milestones
Next Steps
- WP1 - Student System approval provided and set up EPPN
- WP8 - Meeting to be scheduled with St Andrews University
- WP4 - Arrange meeting with RSO and RGS together with HR resource
- Close project
The project Status is AMBER due to delays in progressing Work Packages as project resource on leave and other project and business priorities
| TBC | WP1 Delivery |
| TBC | WP4 Delivery |
| TBC | WP8 Delivery |
| TBC | Project Closure |
- Approved budget
- 25.0 days
- Activity this month
- 0.3 days
- Activity this year
- 14.7 days
- Activity to date
- 14.7 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 8.0 days