Report for July 2017

Report Date
July 2017

Achievements in Last Period

  • Project Brief approval completed
  • WP1 required approval for use of UUN@ed.ac.uk for Staff this is needed from HR which has been provided, for students we require confirmation from Student Systems - data form has been provided and awaiting further details from approval area.
  • WP8 RIS have provided guidance information and activity requires Dev Tech resource with possible Apache2 skills

Issues

  • Delay in project brief sign off due to PM and intern on annual leave - this has now been approved
  • WP8 Meeting held with DevelopmentTechnology and RIS resource to understand fuller requirements of this activity, however concerns raise that there may be more depth work required. Agreed to arrange a meeting with St Andrews University colleagues who are looking at this at present, this will help gauge if this actually need a larger project and more funding to complete.
  • WP4 still to be investigated, likelihood this will be a business process and no technical resource required
  • Review impact of delay and unplanned budget required for next financial year 17/18 review with Programme Owner and Business Lead, revise project milestones

Next Steps

  • WP1 - Student System approval provided and set up EPPN
  • WP8 - Meeting to be scheduled with St Andrews University
  • WP4 - Arrange meeting with RSO and RGS together with HR resource
  • Close project

The project Status is AMBER due to delays in progressing Work Packages as project resource on leave and other project and business priorities

 

TBC WP1 Delivery
TBC WP4 Delivery
TBC WP8 Delivery
TBC Project Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
ISSUE - project status is AMBER due to delays in progressing Work Packages as project resource on leave and other project and business priorities
Change Status
Activity
Approved budget
25.0 days
Activity this month
0.3 days
Activity this year
14.7 days
Activity to date
14.7 days
Estimate to complete current year
2.0 days
Estimate to complete future years
8.0 days

Project Info

Project
Research Information Management - Small Enhancements
Code
RES063
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
22-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Apr-2018
Programme Priority
6
Overall Priority
Normal
Category
Discretionary