Report for May 2017
- Report Date
- May 2017
Achievements in Last Period
- Service owner and key stakeholders agreed to de-scope all work packages - except for WP1, WP4 and WP8
- Dev Tech resource made available for WP8 - Snowball Metrics task
- Remaining work on WP1 and WP4 on hold while focus has been on higher priority work on RES064, RES066 , RES060 and STU252
Issues
- RED - Planning delayed ( PM and business leads - resource conflict)
- Student intern will be assigned to complete the remaining work packages and close the project
- Service owner has escalated WP1 - single-sign-on for Research Professional
Next Steps
- complete planning for work packages : WP1, WP4 and WP8
- deliver WP1
- deliver WP4
- Deliver WP8
- Close project
Milestones
- End of Planning - 16-June 2017
- Approved budget
- 25.0 days
- Activity this month
- 0.2 days
- Activity this year
- 13.5 days
- Activity to date
- 13.5 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 0.0 days