Report for Aug 2016
- Report Date
- August 2016
Achievements in Last Period
- Budget agreed and Project started
- Initial 6 work packages agreed with business stakeholders
Issues
None
Next Steps
- complete planning for each Work package
- schedule work in priority order
Milestones
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 53.0 days
- Estimate to complete future years
- 0.0 days