Report for Aug 2016

Report Date
August 2016

Achievements in Last Period

  • Budget agreed and Project started
  • Initial 6 work packages agreed with business stakeholders

 

Issues

None

Next Steps

  • complete planning for each Work package
  • schedule work in priority order

 

Milestones

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
2.0 days
Activity this year
2.0 days
Activity to date
2.0 days
Estimate to complete current year
53.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Research Information Management - Small Enhancements
Code
RES063
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Start Date
22-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Apr-2018
Programme Priority
6
Overall Priority
Normal
Category
Discretionary