Organisation
Work/Task Breakdown
1/ Planning
- Prepare project brief
- Prepare project estimate
- Plan
2/ Business Requirements
- Define requirements
- BRD
3/ System Design
- System Design Specification
- Technical Architecture Document
4/ Build
- Build/Configure
- Upgrade DEV to Oracle 12c
- Upgrade TEST to Oracle 12c
- Production Deployment Checklist
5/ Integration
- Integration testing
6/ Acceptance
- Undertake UAT
- Handover to Production (Prod Deployment Checklist)
7/ Deployment
- Deploy
- CHNAGE FREEZE
- Upgrade LIVE to Oracle 12c
- DSOR
8/ Project Closure
- Closure Report
Resources Skills and Cost
Project Governance
Request for Change: C1605 - 049