Organisation
Work/Task Breakdown
- Prepare BETA, TEST and LIVE environment with authentication
- Document GaSP user process
- Update PURE Operational Document
- Update PURE TAD
- Handover to production management
- Release to LIVE
Please note that resources are in place to deliver according to the milestones.
Resources Skills and Cost
The majority of this project has been covered in the Planning process whilst proving the proof of concept.
Resource used to date: 16 days
Resource to be completed: 5 days