Impact

 

Priority and Funding

This project is Core funded from the 15/16 plan.

The project will be initiated as a priority 2 during the analysis phase and may reduce to a priority 3 for the remaining work. This will be reviewed as the project progresses. 

 

Impact and Dependencies

The Procurement Team are heavily involved in the PPS008 eCommerce project to move to a single procurement solution. The Procurement team are also required to undertake development work on the process for adding new suppliers via FPM. If the plan for either project changes then there could be an impact to this work. However, the IS Apps work could still progress so this may be minimal. 

 

There are no known dependencies.  

 

Ref Title Impact Probability Risk Status Risk Owner Date of Last Review  
1 Availability of resources - IS Medium Medium AMBER Open Nikki Stuart 06-Jul-2016

view

2 Communication of the purchasing process across the University High Low AMBER Open Craig Henderson 06-Jul-2016

view

3 Availability of staff to discuss the "as-is" procurement process High Medium AMBER Open Craig Henderson 06-Jul-2016

view

4 Other Procurement projects impact the Procurement Teams availability of input to this project Medium Medium AMBER Open Craig Henderson 06-Jul-2016

view

5 Drupel knowledge within the Procurement team may be insufficient Medium Medium AMBER Open Craig Henderson 06-Jul-2016

view

6 Graphic Design Team May Charge for input to Procurement website Medium Medium AMBER Open Nikki Stuart 15-Jul-2016

view

Project Info

Project
Procurement Journey and Online Training
Code
PPS010
Programme
Z. Procurement (PPS)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Withdrawn
Start Date
14-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jul-2018
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation

Plan