Project Summary:

This project undertook a detailed review of the current Procurement Office website, utilising information gathered via an online survey, Google Statistics and by reviewing the procurement websites of other Universities.

A summary of the analysis findings was collated into a review document, which has been handed to Procurement Office for distribution and action.  The supporting data has been supplied so that  this can be used as a baseline for further reviews in the future.

The project lasted longer than was originally anticipated due to conflicts for the stakeholder's time from 'business-as-usual' activities, but the actual days of effort spent was significantly lower than expected (see comments below Resource Usage figures).

The project has helped Procurement Office to gain a good understanding of how their website is being used and by whom.  This valuable information will allow them to further develop the Procurement website to meet the needs of their audience.  It also acts as a baseline so that the impact of any enhancements can be measured. 

Deliverables achieved

DeliverableAchieved?
An online survey to obtain feedback from users of the current siteY
A website strategy document

N

A draft document was started by the project but it was subsequently agreed that this work would be better undertaken by Procurement Office

A review & recommendation document

Y
Map of existing website Y
Summary & analysis of user feedback on the existing site, including online survey results, summary & analysis of Google Analytics dataY

Map of proposed website

N

it was agreed that this work would be better undertaken by Procurement Office

Proposal for elements to be removed

Y

Proposed design

Y

Quick wins

Y

Baseline of current site usage that can be used by Procurement Office to measure impact of changes

Y
Images to support the proposed designY

 

Analysis of Resource Usage:

Staff Usage Estimate: 50 days

Staff Usage Actual: 17 days

Staff Usage Variance: -66%

Other Resource Estimate: 0 days

Other Resource Actual: 0 days

Other Resource Variance: 0%

Explanation for variance:

  • Procurement Office were able to undertake the keying of the online survey and the extract of Google Analytics data themselves, which reduced the effort required from IS Apps

Key Learning Points:

  • Web expertise resources in Service Management were difficult to secure due to the re-structure of IS. This team could have extracted and analysed the data more effiectively.

Outstanding issues:

  • Craig Henderson to produce strategy paper to manage future updates to the website
  • Dawn Nicholls to forward MSExcel spreadsheets of survey data and Google Analytics data to Procurement Office - Done 16/10/14
  • Dawn Nicholls to extract email details from the online survey and forward to Procument Office - Done 16/10/14
  • Dawn Nicholls to forward final versin of review paper to Procurement Office for distribution - Done 16/10/14

Project Info

Project
Procurement Website Developments
Code
PPS007
Programme
Z. Procurement (PPS)
Project Manager
Dawn Holmes
Project Sponsor
Karen Bowman
Current Stage
Close
Status
Closed
Start Date
28-Apr-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Oct-2014