Title Description Author Post date
eCommerce - Team Meeting 14th February

 

Attendees: Nikki Stuart, David Watters, Craig Henderson, Simone Martin, Jeff Borthwick, Dorothy Cunningham

 

Update

Nikki updated the team that, with agreement from Craig, the project milestones had been rescheduled. As the Sciquest license had been extended past November this hard milestone for the implementation was no longer a target. The aim is to deliver the outcomes from the Business Case project within 12/13. 

 

Nikki Stuart 14-Feb-2013
eCommerce - Team Meeting 4th Dec 2012

 

The Project Team met to review progress of Consulations and agree next steps. 

Update on Consultations

  • The face to face consultations will complete on 4th December
  • Feedback has been positive with users accepting the reasons for the review of services
  • Areas where users have reported concerns with current system could be improved if Procurement were able to focus on a single system

 

Questionnaire 

Nikki Stuart 05-Dec-2012
eCommerce Brief Review meeting

eCommerce Brief Review meeting

took place 8-Oct-12

Anne Mathison 08-Oct-2012
Project Team PPS003

Apps Support  -  Anne Finnan (to be confirmed)

Config   -  Defung Ma (initially then a new person to be confirmed)

Dev Tech -  Iain Fiddes  (to be confirmed)

Project Manager   -  Nikki Stuart

Business Analyst  -  David Watters

Anne Mathison 13-Sep-2012

Project Info

Project
eCommerce - Business Case
Code
PPS003
Programme
Z. Procurement (PPS)
Project Manager
David Watters
Project Sponsor
Karen Bowman
Current Stage
Close
Status
Withdrawn
Start Date
03-Sep-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jun-2014
Programme Priority
1
Overall Priority
Normal
Category
Compliance