Report for October
- Report Date
- October 2017
Achievements
- Project budget agreed
- Deployment Sign off Review completed
- Project Closure report completed and signed off by WIS 27-Oct-2017
Issues
- None
Next Steps:
- None
Project RAG status of BLUE
- Approved budget
- 115.0 days
- Activity this month
- 2.0 days
- Activity this year
- 12.0 days
- Activity to date
- 110.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days