- Report Date
- August 2017
Achievements
- Knowledgeable Contractor developer agreed to complete the work off site (including one day on site)
- Retro Arrears project re-started with project extending into 17/18
- Development moved forward and has been completed in August
- Testing is in progress with initial feedback under way
- UAT is in progress
- Business have requested that the Retro Arrears is planned for September payroll
- Hoped to have UAT successfully signed off by 1-Sep, however some amendments arrived on 1-Sep, so currently being tested
- Meeting held on 1-Aug to review options, 2 options were agreed.
Issues:
Next Steps:
- UAT to be signed off in early September with go live before September payroll
- UAT signed off
- Retro Arrears Go Live (no down time required) before September payroll
- Budget to be agreed and confirmed.
- Approved budget
- 90.0 days
- Activity this month
- 7.0 days
- Activity this year
- 7.0 days
- Activity to date
- 105.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days
This article was published on