Monthly Status report

Report Date
August 2017

Achievements

  • Knowledgeable Contractor developer agreed to complete the work off site (including one day on site)
  • Retro Arrears project re-started with project extending into 17/18
  • Development moved forward and has been completed in August
  • Testing is in progress with initial feedback under way
  • UAT is in progress
  • Business have requested that the Retro Arrears is planned for September payroll
  • Hoped to have UAT successfully signed off by 1-Sep, however some amendments arrived on 1-Sep, so currently being tested
  • Meeting held on 1-Aug to review options, 2 options were agreed.

Issues:

  • Budget to be revised

Next Steps:

  • UAT to  be signed off in early September with go live before September payroll
  • UAT signed off
  • Retro Arrears Go Live (no down time required) before September payroll
  • Budget to be agreed and confirmed.
Project Status
RAG Status
Overall
RED
RAG Commentary
Budget to be agreed and revised
Change Status
Activity
Approved budget
90.0 days
Activity this month
7.0 days
Activity this year
7.0 days
Activity to date
105.0 days
Estimate to complete current year
13.0 days
Estimate to complete future years
0.0 days

Project Info

Project
USS Pension Scheme Changes - Phase 2
Code
PPP008
Programme
Z. Payroll and Pensions (PPP) (closed)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
20-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Normal
Category
Compliance