Report for June 2016

Report Date
June 2016

Achievements in Last Period

  • Project Closure confirmed.
  • Closure announcement published on project website.
  • Article submitted to IS News site.

 

 

Milestones

Target date

Title

Complete

25-Sep-2015

Planning sign-off

Yes

26-Oct-2015

Design Review

Yes

07-Mar-2016

USS deadline for completion in TEST

Yes

16-Mar-2016

Build Review

Yes

23-Mar-2016

Acceptance Review

Yes

01-Apr-2016

Delivery

Yes

30-May-2016

Deployment Review

Yes

06-Jun-2016

Closure

Yes

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
141.0 days
Activity this month
2.0 days
Activity this year
136.0 days
Activity to date
136.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Changes to USS Pension Scheme
Code
PPP006
Programme
Z. Payroll and Pensions (PPP) (closed)
Project Manager
Jill Nicoll
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
28-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
17-Jun-2016
Overall Priority
Higher
Category
Compliance

Documentation