Shared Parental Leave work, 2 security patches + TYE bug fix

Shared Parental Leave

Dev

  • DEV signed off 13-Mar

Test

  • Test moved to TEST 17-Mar
  • Plan to be tested by 20-Mar

Live

 

Provisional Bug Fix for TYE and be in for Shared Parental Leave

Dev

  • Plan DEV to be tested by 27-Mar

Test

  • Plan TEST to be tested by 2-Apr

Live

 

Change Control 952353 has been set up

https://www.mcc.mis.ed.ac.uk/index.cfm?event=record.searchresults

Alert has been created.

Event Booking should not be affected by the 2 security patches, confirmed with Gordon John and Chris McKay, so not covred by Alert this time.

Project Info

Project
HR and Payroll Annual Maintenance 14/15
Code
PPP003
Programme
Z. Payroll and Pensions (PPP) (closed)
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
29-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance