Report for July 2015 - draft
- Report Date
- July 2015
Achievements this period
- password reset deliverable approved
- Remedial build work on erecruitment completed and deployed to TEST
- Testing of erecruitment deliverable approved
- Testing underway of online payslips
- uun/email update deliverables deployed to TEST
Issues
- PAY29 report JIRA issue
- Lack of suitable developer resources (eg to cover training or leave ) remains an issue
- Developer resources conflicting with higher priority projects ( eg HRS085)
- acceptance sign-off at risk due to lack of developer resource to resond to issues identified in UAT
- acceptance sign-off at risk due to business resource testing requirements ( unexpected absence and requirement to retest after UAT fixes)
Next Steps
- resolve known JIRA issues
- User Acceptance Testing to complete, including IS testing of uun/email updates
- Agree deployment signoff criteria with business (due to business decision to continue delivering paper payslips for transition period after delivery date)
Milestones
29-Jul-2015 | Acceptance Review |
10-Aug-2015 | Delivery |
07-Sep-2015 | Deployment Sign off Review |
14-Sep-2015 | Close |
RAG Status
The project RAG status is AMBER as the acceptance milestone is at risk due to likely conflicts for developer availability
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days