Report for May 2015
- Report Date
- May 2015
Achievements this period
- new milestones agreed with project sponsor and endorsed by business partners
- password reset build review approved
- password reset deployed to TEST
- UAT plan circulated for approval
- Alternative business tester for HR appointed (due to Annual leave of HR business lead)
Issues
- Text issue with PAY29 report identified
- Lack of suitable developer resources remains an issue
- Build of e-recruitment changes not completed due to issues encountered and conflict for developer resource
- Developer resources at risk of conflict from higher priority projects
Next Steps
- complete build of erecruitment interface
- Deployment to TEST of erecruitment interface to complete
- User Acceptance Testing to proceed
Milestones
22-Jun-2015 | Acceptance Review |
06-Jul-2015 | Delivery |
17-Aug-2015 | Deployment Sign off Review |
24-Aug-2015 | Close |
RAG Status
The project RAG status is GREEN
- Approved budget
- 145.0 days
- Activity this month
- 21.0 days
- Activity this year
- 117.0 days
- Activity to date
- 117.0 days
- Estimate to complete current year
- 28.0 days
- Estimate to complete future years
- 3.5 days