Report for March 2015
- Report Date
- March 2015
Achievements this period
- Build stage under way
- Design of password reset deliverables under way
- Change in project priority to priority 2 agreed
Issues
- Issue relating to adding emails for users not registered in EDDIR might have caused disruption to HR comms processes resulted in delay to build work
- Build work delayed due to loss of resources due to forthcoming departure of development lead
- Additional handover time required from development lead
- Build review delayed till late April
- Current agreed milestones may not be achievable
Next Steps
- Build review to be held
- Investigation into inbuilt password reset to be carried out
- Deployment to TEST to proceed
- Current milestones to be confrmed, or new milestones to be agreed.
Milestones
30-Mar-2015 | 19-Mar-2015 | Build Review |
16-Apr-2015 | 16-Apr-2015 | Build review password reset |
18-May-2015 | 04-May-2015 | Acceptance Review |
08-Jun-2015 | 18-May-2015 | Delivery |
09-Jul-2015 | 08-Jun-2015 | Deployment Sign off Review |
17-Jul-2015 | 06-Jul-2015 | Close |
The project status is AMBER as the build review has not yet been approved and this may result in delays to the delivery milestone. Similarly the project re-estimate to be carried out at the build review cannot yet be completed.
- Approved budget
- 120.0 days
- Activity this month
- 37.0 days
- Activity this year
- 81.0 days
- Activity to date
- 81.0 days
- Estimate to complete current year
- 46.0 days
- Estimate to complete future years
- 5.0 days