Report for February 2015
- Report Date
- February 2015
Achievements this period
- Agreement reached to split design review into two stages, allowing password reset work to be designed separately
- BRD updated as a result of design investigations
- Design review for main deliverables held
- New milestones agreed
Issues
- Key developer resource conflicted for by RES055 ( RMAS person) project resulted in delay to design milestone signoff
- Resourcing issues due to resignation of key USD developer resource resulted in new project milestones being required
Next Steps
- Build stage to commence
- Design of password reset deliverables to commence
Milestones
30-Mar-2015 | 19-Mar-2015 | Build Review |
16-Apr-2015 | 16-Apr-2015 | Build review password reset |
18-May-2015 | 04-May-2015 | Acceptance Review |
08-Jun-2015 | 18-May-2015 | Delivery |
09-Jul-2015 | 08-Jun-2015 | Deployment Sign off Review |
17-Jul-2015 | 06-Jul-2015 | Close |
The project status is AMBER as the design review has not yet been approved.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days