Report for January 2015
- Report Date
- January 2015
Achievements this period
- Brief, estimate and plan redrafted and agreed by project team and business
- BRD circulated and signed off by project team and business
- Purchase of additional requiredoracle self-service licenses agreed
Issues
Key developer resource conflicted for by RES055 ( RMAS person) project risks delay to design milestone
Next Steps
System design stage to be carried out and signed off (PPBR)
Build stage to commence
Milestones
20-Jan-2015 | End of Planning |
30-Jan-2015 | Analysis Review |
26-Feb-2015 | Design Review |
19-Mar-2015 | Build Review |
16-Apr-2015 | Build review password reset |
04-May-2015 | Acceptance Review |
18-May-2015 | Delivery |
08-Jun-2015 | Deployment Sign off Review |
06-Jul-2015 | Close |
The project status is AMBER due to the risk that the conflict for key designer resource will delay design stage
- Approved budget
- 118.0 days
- Activity this month
- 14.5 days
- Activity this year
- 28.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 90.0 days
- Estimate to complete future years
- 0.0 days