Report for April 2017
- Report Date
- April 2017
Achievements this period
- Communications plan for P60s agreed with Payroll and HR business owners
- Communications strategy for future self-service announcements agreed with Payroll and HR business owners
- Discussion re suitability of oracle-self-service for future uses held between IS, Payroll and HR business owners
- Alternative solution for providing online payslip information estimated by IS
Issues
- Project is over budget due to need to resolve new JIRA issue identified in LIVE environment
- Suitability of self-service for additional use in future to be taken forward outwith this project
- Alternative solution to provide online payslip information to be taken forward outwith this project
Next Steps
- Agree budget increase
- Sign off and deploy remaining fix
- Release online P60s to users
- Deployment sign-off
- Close
Milestones
Deployment sign off review 15-May-2017
Closure 29-May-2017
- Approved budget
- 304.0 days
- Activity this month
- 3.0 days
- Activity this year
- 64.0 days
- Activity to date
- 305.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days