Report for March 2017
- Report Date
- March 2017
Achievements this period
- API run in LIVE
- Several JIRA issues closed
- Investigation into poor performance of self-service portal at peak times continued
- Load-testing carried out with colleagues in IS, Payroll and HR
- Changes deployed to LIVE and performance improved during March Payroll period
- Agreement reached to increase budget allowing extension of project till after April payroll period and delivery of P60s ( expected in early May)
Issues
Next Steps
- Resolve remaining JIRA issues
- Release online P60s to users
- Deployment sign-off
- Close
Milestones
Deployment sign off review 15-May-2017
Closure 29-May-2017
- Approved budget
- 304.0 days
- Activity this month
- 15.0 days
- Activity this year
- 61.0 days
- Activity to date
- 302.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days