Report for February 2017
- Report Date
- February 2017
Achievements this period
- Several JIRA issues resolved
- Investigation into poor performance of self-service portal at peak times continued
- Load-testing plan drafted
Issues
- API not yet run in LIVE
- Several JIRA issues not yet resolved and deployed
- Continued poor performance experienced by some users of self-service portal during periods of peak activity
- Additional budget required to deliver new scope and complete project
- Project closure delayed to ensure performance is acceptable during March payroll
Next Steps
- Run API in LIVE
- New scope, budget and milestones to be agreed
- Resolve performance issues
- Resolve remaining JIRA issues
- Deployment sign-off
- Close
Milestones
Deployment sign off review 30-Mar-2017
Closure 21-April-2017
- Approved budget
- 274.0 days
- Activity this month
- 10.0 days
- Activity this year
- 35.0 days
- Activity to date
- 276.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days