Report for February 2017

Report Date
February 2017

 

Achievements this period

 

  • Several   JIRA issues resolved
  • Investigation into poor performance of self-service portal at peak times continued
  • Load-testing plan drafted

Issues

 

Next Steps

 

  • Run API in LIVE
  • New scope, budget and milestones to be agreed
  • Resolve performance issues
  • Resolve remaining JIRA issues
  • Deployment sign-off 
  • Close

 

Milestones

Deployment sign off review 30-Mar-2017

Closure 21-April-2017

 

 

Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
RAG Commentary
ISSUE - performance issues at peak times have not yet been resolved. The duration of the project will be extended and a new budget will be agreed to allow this work to complete.
Change Status
Activity
Approved budget
274.0 days
Activity this month
10.0 days
Activity this year
35.0 days
Activity to date
276.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Online Payslips and P60s
Code
PPP002
Programme
Z. Payroll and Pensions (PPP) (closed)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
21-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2017
Overall Priority
Normal
Category
Discretionary