Report for January 2017
- Report Date
- January 2017
Achievements this period
- Paper payslips (for users without special arrangements) discontinued and January online payslip delivered
- Several JIRA issues resolved
Issues
- Poor performance experienced by some users of self-service portal during periods of peak activity
- Fix tested and deployed
- Project closure delayed to ensure performance is acceptable during February payroll
Next Steps
- Deployment sign-off
- Close
Milestones
Deployment Signoff: 3 March 2017
Closure: 10 March 2017
- Approved budget
- 274.0 days
- Activity this month
- 10.0 days
- Activity this year
- 35.0 days
- Activity to date
- 276.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days