Report for December 2016
- Report Date
- December 2016
Achievements this period
- December payslips published online in parallel with paper payslips
- One LIVE JIRA issue resolved
- Several JIRA issues progressed, awaiting testing
Issues
- Several JIRA issues are unresolved (awaiting testing) but not expected to delay closure
- API will not be run till 17/1/2017 to allow time for above JIRAs to be deployed to LIVE first.
- Project contingency used resolving JIRA issues uncovered in LIVE. Risk of project exceeding budget has increased.
- Unavailability of DEV due to PPP010 development work may delay completion of JIRAs and delay closure
Next Steps
- Business to complete parallel run
- Deployment sign-off
- Close
Milestones
31-Jan-2016 | Deployment Sign off Review |
10-Feb-2016 | Close |
RAG Status
The project status is AMBER
- Approved budget
- 274.0 days
- Activity this month
- 1.0 day
- Activity this year
- 24.0 days
- Activity to date
- 265.0 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days